On May 11th, Resolution No. 287/17 (the “Resolution”) of the Secretariat of Electric Energy (the “SEE”) was published, initiating the first round of tenders (“Stage I”) arising from the “Expressions of Interest” procedure called by Resolution SEE No. 420/16.

The Resolution approved the Tender´s Terms and Conditions (the “Bid Document”), including a draft of the Power Purchase Agreement (“PPA”) to be executed between bidders awarded in the Tender and the Wholesale Electric Market Management Company (“CAMMESA” or the “Off-taker”).

Projects included in Stage I:

  1. Close cycle gas turbine projects that: (i) currently operate or will be shortly in operation in simple cycle; (ii) have low specific consumption; (iii) are likely to improve its efficiency with the close cycle; (iv) do not affect transmission capacity; (v) have the necessary infrastructure to enable the permanent operation of the combined cycle and (vi) have a maximum term of construction of thirty (30) months.
  2. Co-generation projects that: (i) are efficient; (ii) do not affect transmission capacity; (iii) have available supply of the main and alternative fuel and (iii) have a maximum term of construction of thirty (30) months.

The main features of the projects allowed to participate in Stage I are outlined in Section II, Title I of the Bid Document.

New combined-cycle power plants and transmission and fuel supply projects will be contracted through future tenders.

Main aspects of the Bid Document:

  • Bid Bond: Among the formalities bidders should comply with, a bid bond equal to UDS 5.000 x the net power capacity (MW) offered should be submitted.
  • PPA´s term: 15 years.
  • Price: Seller will be entitled to collect a fixed price for the power availability established in US dollars per MW/month and a variable price for the energy produced established in US dollars per MW/hour. Such price will be paid in Argentine Pesos at the rate established in the PPA.
  • Fuel: If bidders offer alternative fuel, Buyer will monthly pay for such fuel calculated in accordance with the “The Procedures for Programming the Operation, the Dispatch and calculation of prices” and the reference prices detailed in Section II, Chapter 9 of the Bid Document.
  • Penalties: The PPA establishes daily penalties for not reaching Commercial Operation Date (“COD”) up to sixty (60) days from the estimated date included in the Offer. If COD is not reached within one hundred and eighty (180) days from the estimated date, the PPA shall be terminated. The penalty regime is equal to the one established under Resolution SEE No. 21/16.
  • Interconnection point: Section II, Chapter 7 of the Bid Document details the possible interconnection points to the Argentine Interconnection System, its maximum power capacity and loss factors.
  • Special Fund: An innovation compared to the PPAs under Resolution SEE No. 21/16 is given by the future incorporation of a special fund to secure six (6) month payments under the PPA. The features of this fund are to be stipulated in the following months.

Stage I schedule is as follows:

  • Q&A period: up to July 7th, 2017.
  • Bid submission and opening of envelope 1: July 19th, 2017 at 13.00.
  • Opening of envelope 2: August 9th, 2017.
  • CAMMESA´s prequalification: August 30th, 2017.
  • Execution of the PPA: no later than November 1st, 2017.

The Bid Document may be amended by the SEE through additional communications (“Circulares”).

For further information, please do not hesitate to contact us.